Expansion of the plaster area

- Destination: Expansion of the plaster area, installation of pipelines and pumping stations
- Contract sum: 2.5 million euro
- Construction period: 24 months
- Subscriber: E. Hartikainen Oy / Yara Finland
- Subcontractor:
- Construction of pressure pipelines for the expansion of the plaster area and underground pressure pipelines for the new recirculation basin.
- Construction of pump stations, 13 units.
- Pipe sizes 110-630 HDPE, quantity approx. 4 km.
- Safety and how to consider it when working on the factory floor.
- Installation of service trenches.