Expansion of the plaster area  

Expansion of the plaster area  

  • Destination: Expansion of the plaster area, installation of pipelines and pumping stations
  • Contract sum: 2.5 million euro
  • Construction period: 24 months
  • Subscriber: E. Hartikainen Oy / Yara Finland
  • Subcontractor:
    • Construction of pressure pipelines for the expansion of the plaster area and underground pressure pipelines for the new recirculation basin.
    • Construction of pump stations, 13 units.
    • Pipe sizes 110-630 HDPE, quantity approx. 4 km.
    • Safety and how to consider it when working on the factory floor.
    • Installation of service trenches.
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.